The Errea Wittu Floating Production, Storage and Offloading (FPSO) vessel has achieved First Oil, according to a press release from the Ministry of Natural Resources on November 16.
This marks the start-up of the Uaru Development, the fifth offshore development in the Stabroek Block. Errea Wittu, a Warrau word meaning โabundance,โ will produce oil under the Uaru Petroleum Production Licence granted on April 27, 2023.
ExxonMobil Guyana said that Uaru has raised Guyana’s installed production capacity to approximately 1.1 million b/d.
The vessel was built by MODEC, and is the first vessel built by that company for Guyana. It will be located approximately 200 kilometres offshore Guyana. It has a storage capacity of approximately two million barrels of crude oil and is constructed on a new-build hull and moored using a SOFEC spread mooring system. Its topsides are designed to handle up to 540 million cubic feet of associated gas per day and support water injection of up to 350,000 barrels per day.
The vessel will produce approximately 250,000 barrels of oil per day (bpd) and will add to Guyana’s total daily crude output which is expected to rise from just over 900,000 bpd to approximately 1.15 million bpd. It will combine development of the Snoek, Mako and Uaru resources with production from 44 production and injection wells across up to 10 drill centers, the Ministry said.
(Click here to read about the people behind the Errea Wittu.)