ExxonMobil’s Guyana oil ventures: A roadmap to 1.7 million b/d

Related Articles

Published by OilNOW on December 30, 2024

With more than 30 discoveries made offshore Guyana, ExxonMobil has a line of sight for the addition of eight floating production, storage, and offloading (FPSO) vessels by 2027, a goal that is expected to see oil production reach 1.7 million barrels per day (b/d).

All projects will be located in the Stabroek Block, in which ExxonMobil holds a 45% operating stake. Hess (30%) and CNOOC (25%) are its co-venturers.

Liza Phase 1

The Liza Destiny FPSO

Field(s): Liza

Resource: 450 million barrels of oil

Development wells: 17

First Oil: December 2019

Oil Production Capacity: 160,000 b/d

FPSO Oil Storage Capacity: 1.6 million barrels

Offloading Frequency: Every 5 – 10 days

Estimated Development Cost: US$3.6 billion

Liza Phase 2

The Liza Unity FPSO

Field(s): Liza

Resource: 600 million barrels of oil

Development wells: 33

First Oil: February 2022

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$6 billion

Payara

The Prosperity FPSO

Field(s): Payara, Pacora

Resource: 600 million barrels of oil

Development wells: 35 – 45

First Oil: November 2023

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$9 billion

Yellowtail

The hull for the Yellowtail FPSO, to be named ONE GUYANA

Field(s): Yellowtail, Redtail

Resource: 925 million barrels of oil

Development wells: 45 – 55

First Oil: 2025 (Expected)

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$10 billion

Uaru

MODEC’s M350 – Next Generation new build hull to be utilized for the Uaru project FPSO

Field(s): Uaru, Mako, Snoek

Resource: 800 million barrels of oil

Development wells: 40 – 76

First Oil: 2026 (Expected)

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Every 4 days

Estimated Development Cost: US$12.7 billion

Whiptail

An SBM Offshore multi-purpose floater hull reserved by ExxonMobil for a future Guyana FPSO

Field(s): Whiptail, Pinktail, Tilapia

Resource: 850 million barrels of oil

Development wells: 33 – 72

First Oil: Late 2027 – Early 2028

Oil Production Capacity: 250,000 b/d

FPSO Oil Storage Capacity: 2 million barrels

Offloading Frequency: Approximately every 3-6 days

Estimated Development Cost: US$12.7 billion

Hammerhead (Seeking approval)

Named after the Hammerhead shark, Exxon’s seventh Guyana project will tap its ninth Stabroek Block discovery.

Field(s): Hammerhead

Development wells: 14 – 30

First Oil: 2029

Oil Production Capacity: 150,000 b/d

FPSO Oil Storage Capacity: 1.4 million barrels

Longtail (Announced)

Crew onboard the Liza Destiny FPSO preparing to offload crude to a tanker, at the Stabroek block, offshore Guyana.

Field(s): Longtail

First Oil: 2030

Oil Production Capacity: 240,000 b/d